• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2016 - Apr 2017
  • Estimated project cost $634,893
  • Australian Government contribution $340,699
  • Local Council/Shire Shire of Cue
  • State WA

Project description

Road surface is uneven and the bitumen seal is lifting away causing pot holes.

The base course and surface seal are to be recycled using a stabilising machine and used to prepare a new base course. The surface is to be sealed using a sand seal from local materials.

Total cost of proposed project is $634,893

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.