• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2017 - Sep 2017
  • Estimated project cost $135,704
  • Australian Government contribution $135,704
  • Local Council/Shire City of Lithgow Council
  • State NSW

Project description

Severe potholing and rutting of the asphalt surface as well as severe edge breaking and depressions. Stormwater drainage is poor in these areas leading to the degradation of seal.

Affected areas will have their seal removed and subsurface remediated. Seal will then be replaced. Shoulders will be replaced/widened in areas and roadside drainage will be improved to ensure the proper flow of stormwater.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.