• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2016 - Dec 2016
  • Estimated project cost $35,502
  • Australian Government contribution $11,332
  • State NT

Project description

safety of children walking along the school road build up of water in the drains during the wet season making the drains unsafe and creating flooding over the road - drains being unsafe for children

Part A of the road work is a joint project with the Dept of Education *install speed humps either ends of the road, install school signs and speed signs *install bollards along the school fence side of the road to create a defined walking path for the children - there is no defined walking path on Wudanbaiya road Part B Clean out the drain on the east end of the road - this is a large drain area that builds up very quickly with foliage - either side of the drain to be widened, remove all foliage and install a removable grate either entrance of the concrete drain *clean out the drain

Total cost of proposed project is $35,502

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.