• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2016 - Aug 2016
  • Estimated project cost $590,000
  • Australian Government contribution $490,000
  • State NSW

Project description

Has been listed on numerous occasions for Federal and State Blackspot grant funding to address the traffic and pedestrian safety issues for the location. Peak hour buildup of traffic; significant accident reports; requests by Disabled and Access restricted community groups;

Substantial utility relocation; subsoil drainage, drainage kerb inlets and upgraded stormwater lines; relocation of gas utility; removal and replacement of kerb returns; placement of new roundabout annulus island; granular pavement and asphalting or full depth asphalt pavement.

Total cost of proposed project is $590,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.