• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2016 - Jun 2017
  • Estimated project cost $235,890
  • Australian Government contribution $31,039
  • Local Council/Shire Sunshine Coast Regional Council
  • State QLD

Project description

The proposed sections have the following defects: moderate crocodile cracking, heavy patching, ravelling, oxidation and weathering due to the age of the existing surface. The surface of the road has moderate failures (for example, potholes and patches).

2 Coat double/double seal: Profile edges to key-in with the concrete kerb and channel; Waterproofing and crack alleviation bitumen sprayed seal; and 2 coat double double (using size 14mm/7mm nominal aggregate).

Total cost of proposed project is $235,890

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.