• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2016 - Mar 2017
  • Estimated project cost $247,662
  • Australian Government contribution $231,062
  • Local Council/Shire Wollondilly Shire Council
  • State NSW

Project description

Pavement is rutted and rough, with several failures and potholes, with narrow shoulders. Maintenance costs are high and the amenity provided is low.

Rip the existing surface, spread 200 mm granular material (widening the shoulders where required) and finish with a 2 coat seal

Total cost of proposed project is $247,662

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.