• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2016 - Apr 2017
  • Estimated project cost $169,445
  • Australian Government contribution $169,445
  • Local Council/Shire Penrith City Council
  • State NSW

Project description

The road was originally constructed in 1978 and is showing signs of failure with numerous patches due to the aging of asphalt and increasing traffic volume

It is proposed to mill existing pavement to a depth of 130mm and to provide 130mm deeplift asphalt pavement for a length of 350 metres and a width of 12 metres

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.