• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2017 - Jun 2017
  • Estimated project cost $128,391
  • Australian Government contribution $57,387
  • State SA

Project description

Sheeting surface has reached end of service life and requires renewal to prevent sub course damage and ensure safe vehicle transport at posted speed limit.

Resheet the surface and rectify sub course damage were required

Total cost of proposed project is $128,391

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.