• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2017 - Apr 2018
  • Estimated project cost $127,080
  • Australian Government contribution $127,080
  • Local Council/Shire Shire of Brookton
  • State WA

Project description

Poor alignment causing safety issue

Resume land, clear inside corner (clearing permits obtained), fence and survey new alignment, prepare sub base, cart minimum 200mm base course material, prime seal to 7metres width on 9 metre formation. Install culverts as required, widen culverts as required. Safety devices (guide post signs) as required.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.