• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2017 - Sep 2017
  • Estimated project cost $1,299,733
  • Australian Government contribution $259,733
  • Local Council/Shire Byron Shire Council
  • State NSW

Project description

Road has extensive potholing and sections of failed pavement, insufficent surface drainage (defective kerb and gutter in places) and no drainage of subsoil.

Replacement of defective kerb and gutter. Placement of subsoil drainage along the length of the 1.0km corridor. Remove 190mm of existing pavement and replace with 190mm AC along 850m of the corrridor from Warambool and Orana Road intersection west. Western 150m of works area on Orana Road to be milled 45mm and replaced with 45mm AC14.

Total cost of proposed project is $1,299,733

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.