• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2017 - Oct 2017
  • Estimated project cost $191,400
  • Australian Government contribution $70,000
  • Local Council/Shire City of Subiaco
  • State WA

Project description

Pavement wearing surface failure reflecting in the form of longitudinal and transverse cracking

Profile the existing pavement by 20-25mm and replace it with 7mm aggregate size 30mm thick Stone Mastic Asphalt, Total pavement area- 4400m2

Total cost of proposed project is $191,400

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.