• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2017 - Dec 2017
  • Estimated project cost $576,990
  • Australian Government contribution $413,485
  • State WA

Project description

Age, poor drainage and cracked kerb with sections missing and displaced

Asphalt, localised profiling, localised kerb replacement and pit lid realignment

Total cost of proposed project is $576,990

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.