• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2017 - Sep 2017
  • Estimated project cost $397,403
  • Australian Government contribution $397,403
  • Local Council/Shire Ku-Ring-Gai Council
  • State NSW

Project description

The road surface and pavement layers underneath have deteriorated to an unsatisfactory standard.

The proposed treatment is to remove and replace the surface and pavement layers with new material to a depth of 100mm.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.