• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2017 - Mar 2018
  • Estimated project cost $1,260,000
  • Australian Government contribution $900,000
  • Local Council/Shire Moreton Bay Regional Council
  • State QLD

Project description

The current drainage system on this road is insufficient for current needs. The road currently has no kerb and channeling and insufficient piped drainage which causes drainage issues in wet weather.

The project includes road reconstruction, provision of piped and upgraded open drainage channels, footpath construction and the implementation of water sensitive urban drainage (WSUD) principles. To upgrade the existing road and drainage networks to provide an appropriate level of service.

Total cost of proposed project is $1,260,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.