• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2018 - May 2019
  • Estimated project cost $175,000
  • Australian Government contribution $165,254
  • Local Council/Shire Central Coast Council
  • State TAS

Project description

Drainage issues, pavement failures.

Improve drainage and reconstruct pavement failures. Length 450m seal width 5.2m

Total cost of proposed project is $175,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.