• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2017 - Nov 2017
  • Estimated project cost $662,000
  • Australian Government contribution $560,000
  • Local Council/Shire Ballina Shire Council
  • State NSW

Project description

Old pavement and very narrow seal has failed showing pavement rutting and shoving with significant heavy patching accompnied by poor drainage, which requires high maintenance resources.

Reconstruction of pavement and seal for a length of approximately 850 metres with a variable seal width (between 5.0 to 6.0 metres) including ten culvert reconstructions and installation of approximately 550 metres of new kerb and gutter.

Total cost of proposed project is $662,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.