• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2017 - Jun 2018
  • Estimated project cost $201,289
  • Australian Government contribution $201,289
  • State NT

Project description

Further poorly constructed without end walls and wings, blocked or collapsed culverts are identified. Problem causes drainage problems and significant road erosion.

Demolish four (4) existing culverts and construct culverts with floor slab, head walls and wings, according to engineering design.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.