• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2018 - Aug 2018
  • Estimated project cost $381,556
  • Australian Government contribution $344,854
  • State NSW

Project description

Excessive cracking

Mill asphalt road pavement 150mm deep. Pave 100 mm AC20 Class 450 and then pave 50 mm AC14 Class 450.

Total cost of proposed project is $381,556

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.