• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2019 - Apr 2019
  • Estimated project cost $477,295
  • Australian Government contribution $477,295
  • State NSW

Project description

Excessive cracking and potholes

In the traffic lanes, mill 100mm asphalt. Pave 50mm AC14 Class 450 (HDA) (base) then pave 50 mm AC14 Class A15E. In the parking lanes, mill 50 mm. Pave 50 mm AC14 Class 450

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.