• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2019 - Feb 2020
  • Estimated project cost $98,744
  • Australian Government contribution $98,744
  • Local Council/Shire City of Lithgow Council
  • State NSW

Project description

Repair of severe defects including potholing and edge breaks.

Removal of the existing seal and reconstruction of the existing pavement by blending additional road base where required. Reconstruction of roadside drainage and reapplication of seal using a 14/7 two-coat bitumen seal at the existing width.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.