• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2019 - Feb 2020
  • Estimated project cost $103,865
  • Australian Government contribution $82,113
  • Local Council/Shire Shire of Dandaragan
  • State WA

Project description

Road has severe cracking issues and rutting in localised areas. Kerbing is cracked and pushing out into the road. Isolated pavement failures need correcting and importing new road base needs to happen to correct surface levels and consolidate drainage improvements.

Remove kerbing/footpath ramps and inspect/clean and/or replace drainage pits as required. Remove bituminous surface and cart away. Reconstruct pavement and import road base as required to correct levels. Apply a 10mm 90/10 primer seal followed by 40mm of dense course asphalt. Install new semi mountable kerbing as prior. Connect footpath ramps as prior.

Total cost of proposed project is $103,865

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.