• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2019 - Dec 2020
  • Estimated project cost $970,176
  • Australian Government contribution $300,000
  • Local Council/Shire Hobsons Bay City Council
  • State VIC

Project description

The pavement has lost shape with failures and cracking along the length of street. Some of the existing kerb and channel has subsided in various locations and hold water. The kerb and channel needs to be reconstructed and new drainage needs to be installed. The pavement requires full reconstruction with asphalt regulation layer and asphalt wearing course to address failures and safety risk to users.

Reconstruction of kerb and channel, installation of new drainage to service road and full width reconstruction of road pavement and asphalt surface to current standards.

Total cost of proposed project is $970,176

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.