• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2019 - Jan 2020
  • Estimated project cost $211,587
  • Australian Government contribution $120,000
  • State NSW

Project description

The asphalt road surface is cracked and failed in many places with rutting and pot holes on the road surface indicating subbase failure

Excavate 50mm deep and resurface the road pavement with 50mm thick asphalt concrete layer. Approximate area to be rehabilitated is 2,470 square metres with dimensions, 215m long x 11.5m wide.

Total cost of proposed project is $211,587

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.