• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - Mar 2020
  • Estimated project cost $199,081
  • Australian Government contribution $199,081
  • Local Council/Shire Hawkesbury City Council
  • State NSW

Project description

Pavement failures comprising rutting, cracking and heaves

Rehabilitate in accordance with the Geotechnical Report

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.