• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2019 - Jan 2020
  • Estimated project cost $92,232
  • Australian Government contribution $92,232
  • State NSW

Project description

The existing road surface is old and oxidised. It is affected by cracks and loss of aggregate particles from existing spray seal, especially at western shoulder. Tree roots have lifted the road surface in some areas and caused it to crack.

The proposed work will include repair of cracked pavement areas and resurfacing of the road with asphalt. Length = 444 m; Width = 8.2 m; Area = 3640.8 m2.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.