• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2019 - Jun 2020
  • Estimated project cost $1,094,721
  • Australian Government contribution $494,721
  • State NSW

Project description

Poor pavement condition is currently resulting in unsafe site conditions. This project will allow improvements to Safety and reduce ongoing reactive maintenance.

Mill and Fill - 150mm of milling and AC (100 AC20 and 50mm AC14) in various sections of the road.

Total cost of proposed project is $1,094,721

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.