• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2019 - Aug 2019
  • Estimated project cost $210,298
  • Australian Government contribution $210,000
  • State QLD

Project description

The current road is a bitumen road with table drains. Underground stormwater has been installed. Kerb and chanelling required to connect with stormwater network and to meet current level of service standard.

Reconstruct road to kerb and chanel standard.

Total cost of proposed project is $210,298

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.