• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2024 - Jun 2024
  • Estimated project cost $919,120
  • Australian Government contribution $919,120
  • State NT

Project description

Water damaged, corrugated and gravel road from Airport Car park, also need drainage system to avoid future rain damage. Dust problem to near by houses.

Upgrade to bitumen seal, install 30m long x 9m wide concrete floodway over small wash out, re- work existing grave pavement to depth of 150mm as new subgrade layer, construct 150 mm gravel pavement. Lnstall kerb and channel on both sides of road.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.