• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mid 2020 - Mid 2021
  • Estimated project cost $7,210,546
  • Australian Government contribution $3,537,066
  • State ACT

Project description

This project restored road pavements along Northbourne Avenue in the following sections:

  • Condamine Street and MacArthur Avenue (Northbound)
  • Antill Street and MacArthur Avenue (Southbound)
  • Mouat Street to Macarthur Avenue (Southbound)

The project involved removing the existing pavement surface and structural layer of pavement, remediating poor condition sub-surface areas and then reconstructing the road pavement.

Benefits

  • Improve road safety for all road users
  • Reduce congestion and improve travel times
  • Improve efficiency and network reliability
  • Improve connectivity between people with jobs and services, and goods with markets
  • Improve accessibility and connectivity of road networks

Funding

The Australian Government committed $5,000,000 to this project. This was reduced to $3,537,066 accounting for realised savings following project completion.

Timetable

Project is complete. Construction commenced in mid-2020, and was completed in mid-2021.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.