• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish July 2021 - Juen 2023
  • Estimated project cost $24,856,998
  • Australian Government contribution $19,885,598
  • State QLD

Project description

The project upgraded 7.7km of the Gregory Developmental Road from Marble Creek to Christmas Creek between Charters Towers to The Lynd. This included widening and strengthening pavement and upgrading drainage structures to improve flood resilience.

Benefits

Improve road safety for all road users
Improve efficiency and network reliability
Improve connectivity between people with jobs and services, and goods with markets
Improve accessibility and connectivity of road networks
Improve freight productivity
 

Funding

The Australian Government committed $19.89 million towards this $24.86 millio  project

Timetable

This project commenced construction July 2021 and was completed in June 2023.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.