• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - Jun 2020
  • Estimated project cost $469,353
  • Australian Government contribution $226,520
  • Local Council/Shire Brimbank City Council
  • State VIC

Project description

The existing road pavement exhibits oxidation and areas of significant cracking, loss of aggregate and longitudinal roughness. In addition, significant lengths of concrete kerbing are in poor condition.

The project includes the following major aspects: • Reconstruction of 300 metres of existing road pavement • Reconstruction of 625 metres of existing kerb and channel • Reconstruction of existing vehicle crossings where required • Reconstruction of all damaged footpath • Construction of 220 metres of underground drainage works

Total cost of proposed project is $469,353

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.