• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2020 - Mar 2021
  • Estimated project cost $179,574
  • Australian Government contribution $179,574
  • Local Council/Shire Campbelltown City Council
  • State NSW

Project description

The road surface is 18 years old and heavily oxidised, affected with significant levels of ravelling and moderate levels of cracking. The length of the road section is 651m, width 11.3m and the proposed treatment area is approximately 7000m2.

The proposed treatment include heavy patching the isolated failed area first followed by inter layer rubber seal with hot-mix asphalt overlay.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.