• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Mar 2021
  • Estimated project cost $43,767
  • Australian Government contribution $43,767
  • Local Council/Shire Coolamon Shire Council
  • State NSW

Project description

Developing section of Coolamon township with insufficient seal width, provision of roadside parking and drainage infrastructure to accept overland flows and eliminated erosion.

Works include extension of seal width to permit two lane two way traffic and roadside parking in addition to installation of kerb and gutter to define road extent and collect and control drainage flows.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.