• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Nov 2020
  • Estimated project cost $244,793
  • Australian Government contribution $244,793
  • Local Council/Shire Wudinna District Council
  • State SA

Project description

The road is currently natural surface and does not provide all weather access. Heavy vehicles have difficulty accessing the road due to the large number of soft sand hills. The natural surface is very rough and water does not adequately drain.

Trees will be trimmed. Create drains. Cut down sand hills. Sheet length of road with introduced crushed rubble. Water crushed rubble and compact, forming surface during construction.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.