• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2020 - Sep 2020
  • Estimated project cost $227,036
  • Australian Government contribution $227,036
  • Local Council/Shire Townsville City Council
  • State QLD

Project description

The first section of this street has moderate deformation in areas, along multiple previous pothole and patch repairs. There is also moderate to severe cracking evident throughout and the kerbs are exhibiting defects.

Remove all existing kerbs and road pavements (full width), treat subgrade with lime stabilization (if required). Full road reconstruction including all kerb and channel.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.