• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2020 - Jan 2021
  • Estimated project cost $95,003
  • Australian Government contribution $95,003
  • Local Council/Shire Strathfield Municipal Council
  • State NSW

Project description

Lots of crocodile cracks throughout the section, rutting. The riding quality and safety of pedestrian and vehicles will be improved once the works are complete. The roughness and skid resistance will be consistent and improve riding comfort.

Mill and fill (AC 10 - 50mm depth) and heavy patching in the failed section with upto 120mm depth with AC 10 - 50mm plus AC 14 - 70mmm.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.