• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2021 - Apr 2021
  • Estimated project cost $157,503
  • Australian Government contribution $150,000
  • Local Council/Shire West Tamar Council
  • State TAS

Project description

The existing triple cell box culvert over Brandy Creek is an aged, dilapidated asset, and replacement is required to maintain the serviceability of the road.

Existing box culvert will be replaced by twin 1809 uni-culverts. Massbloc retaining structures will be placed against the approaches to the new culvert for additional scour protection. Approaches to the bridge will be reconstructed and a side-track placed for the duration of construction. New guardrails will be installed to span the new culvert structure

Total cost of proposed project is $157,503

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.