• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2021 - Jan 2022
  • Estimated project cost $1,584,227
  • Australian Government contribution $1,191,410
  • State NT

Project description

This particular section of road has evidence of pavement failure such as potholes, wheel rutting and edge drop off, with sigs where these failure have previously been repaired.

Ch950 – Ch1550 comprises reconstruction of pavement, stormwater drainage upgradation. Ch475 – Ch 950 comprises widening of the road adjacent the Childcare Centre and Irwin Road intersection to provide road safety improvements and improved manoeuvring. This stage also includes upgradation of the stormwater drainage within Ch475 to Ch950.

Total cost of proposed project is $1,584,227

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.