• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2022 - May 2022
  • Estimated project cost $300,626
  • Australian Government contribution $285,660
  • State QLD

Project description

Existing road is very rough. Road requires renewal to meet current level of service and current standards.

Reconstruct to a 7m formation and 4m seal. Min 300mm deep pavement depth.

Total cost of proposed project is $300,626

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.