• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2023 - Mar 2023
  • Estimated project cost $115,282
  • Australian Government contribution $115,282
  • Local Council/Shire Randwick City Council
  • State NSW

Project description

Road pavement failure evidenced extensive crocodile cracking along travelling lane and road depression.

100mm heavy patching of failed areas and 30mm road resheeting entire road from gutter to gutter.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.