• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2023 - Apr 2023
  • Estimated project cost $295,000
  • Australian Government contribution $295,000
  • Local Council/Shire Sutherland Shire Council
  • State NSW

Project description

Road pavement reached the end of its service life and deteriorated due to road surface and base layer failure. Road is significantly potholed and deformed along wheel path due to water infiltration.

Road pavement reconstruction over approximately 4,500 sqm. Road pavement works include 250mm thick cement stabilised base course and 50mm thick asphalt concrete wearing surface on top.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.