• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2022 - Jun 2023
  • Estimated project cost $470,000
  • Australian Government contribution $289,546
  • Local Council/Shire Central Goldfields Shire Council
  • State VIC

Project description

The pavement is in very poor condition and geotech testing has indicated it needs replacing with new pavement, due to the very poor sub-grades and new bituminous seal; kerb and channel is in a state of failure and will need replacing. Verges, medians and footpaths are very poor and need replacing.

Full reconstruction of the road environment; new 150 cement stabilised sub-base, 160mm pavement crushed rock & 30mm Asphalt, new linemarking, new kerb & channel & pits, restored verges and new footpaths.

Total cost of proposed project is $470,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.