• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2022 - Sep 2023
  • Estimated project cost $893,520
  • Australian Government contribution $682,617
  • Local Council/Shire Brimbank City Council
  • State VIC

Project description

The existing road pavement exhibits oxidation and areas of significant cracking, loss of aggregate and longitudinal roughness. In addition, significant lengths of concrete kerbing are in a poor condition.

The project includes the following major aspects - Rehabilitation of 470 metres of existing pavement and resurfacing with asphalt, reconstruction of 975 metres of kerb and channel, reconstruction of existing vehicle crossings where required, reconstruction of all damaged footpath, construction of 350 metres of underground drainage.

Total cost of proposed project is $893,520

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.