• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2022 - Dec 2022
  • Estimated project cost $162,289
  • Australian Government contribution $80,000
  • State NSW

Project description

Westminster Road pavement has extensive failure approximately 50% of the area. Pavement length is 165m and average width is 10m.

Rehabilitation of the pavement by heavy patching, profiling and resurfacing.

Total cost of proposed project is $162,289

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.