• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2022 - Jan 2023
  • Estimated project cost $705,270
  • Australian Government contribution $617,418
  • Local Council/Shire City of West Torrens
  • State SA

Project description

Pavement, Seal and Kerb have reached there end of useful life

Full reconstruction of Pavement, Seal and Kerb

Total cost of proposed project is $705,270

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.