• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2023 - May 2023
  • Estimated project cost $327,742
  • Australian Government contribution $327,742
  • Local Council/Shire Liverpool Plains Shire Council
  • State NSW

Project description

The road is unsealed. The pavement width varies along the length of the road with substandard drainage in some locations. Gravel depth is minimal with material binder absent over most of the road length causing major corrugations and scouring.

Road pavement is to reconstructed to 6.0m wide. Positive drainage is to be constructed along both sides of the pavement. Placement of 50mm compacted depth of gravel profiled to 4% camber.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.