• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2023 - Jan 2024
  • Estimated project cost $34,440
  • Australian Government contribution $22,500
  • Local Council/Shire City of Subiaco
  • State WA

Project description

Fatigue failure of the pavement wearing surface reflecting in the form of structural longitudinal cracking

Profiling the existing pavement by 25 mm and replacing with Dense Graded asphalt 30mm thick containing 15-18% of crumb rubber ( sustainable asphalt mix)

Total cost of proposed project is $34,440

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.