• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2024 - Jun 2024
  • Estimated project cost $400,000
  • Australian Government contribution $201,819
  • Local Council/Shire Central Darling Shire Council
  • State NSW

Project description

Total road loss in high Darling River and Talyawalka Creek flows resulted in extended road closure times.

Install new reinforced concrete box culverts to relieve pressure in times of flood.

Total cost of proposed project is $400,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.