• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2024 - Mar 2024
  • Estimated project cost $53,767
  • Australian Government contribution $42,446
  • Local Council/Shire Corporation of the City of Norwood Payneham & St Peters
  • State SA

Project description

Road surface is in unsuitable condition and is due for re-seal works. Additionally, adjacent properties are experiencing minor flooding as a result of overland flow coming from this laneway.

Road surface re-seal works will be undertaken for the full length and width of the laneway. A central spoon drain is also to be installed within the laneway to address the minor flooding issue.

Total cost of proposed project is $53,766

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.