• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2023 - May 2024
  • Estimated project cost $142,273
  • Australian Government contribution $142,273
  • Local Council/Shire Huon Valley Council
  • State TAS

Project description

Renew existing road seal that is showing signs of fatigue.

Repair defects and edge breaks as required. Trim vegetation, reseal 1105 meters x 6 meters, replace center line and install guide posts and signage.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.